Project Updates

The Final Design Phase of the Atlantic City Expressway (ACE) Third Lane Widening Project was initiated in January 2025. Site investigations consisting of soil borings and test pits were conducted throughout the project limits in Summer 2025 to confirm existing underground utilities and soil conditions. The Design Team is actively coordinating with the New Jersey Department of Transportation (NJDOT), New Jersey Department of Environmental Protection (NJDEP). New Jersey Pinelands Commission, and local utility stakeholders as the contract documents are being refined throughout the Final Design Phase.

The project is currently being divided into three construction packages. The limits of Contract No. 1 include the widening and associated improvements from the western terminus at Interchange 44 to Interchange 41. Contract No. 2 improvements range from Interchange 41 to Interchange 31 along the Eastbound roadway. Contract No. 3 improvements range from Interchange 41 to Interchange 31 along the Westbound roadway.

In advance of the larger widening improvement contracts, SJTA will be constructing safety and operational improvements that include widening the Sicklerville Road Ramp at Interchange 7 and performing isolated shoulder repairs throughout the Eastbound and Westbound roadways. This construction is anticipated to start in Fall 2026 after the summer peak congestion period.

Previous Project Email Updates

Project Progress

Initial Stakeholder & Public Information Center

Initial Public Comment Period

Selection of Preliminary Preferred Alternative

Environmental Clearances

Advance Preliminary Preferred Alternative

Conduct Preliminary Engineering

Continued Public Outreach & Involvement

Finalize Design and develop Construction Documents

Secure all Environmental Permits

Advertise, Bid and Award Contracts for Construction

Continued Public Outreach & Involvement

ADVANCED CONTRACTS (FALL 2026)
ACE Shoulder Repair MP 31.90 To 40.10
Exit 7 Sicklerville Road Ramp Widening

CONTRACT 1 (2027–2029)
Rt 42 / ACE Interchange To MP 40.0

CONTRACT 2 (TBD)
ACE Eastbound Roadway MP 40.0 To 31.6

CONTRACT 3 (TBD)
ACE Westbound Roadway MP 40.0 To 31.6

Implement & Complete Construction

Two Lanes to be Maintained Each Way

Continued Public Outreach & Involvement

*Notes current phase of project.