Project Schedule

2022

February 16, 2022

Concept Development Public Information Center

Feb

March 2022

Concept Development Complete

Mar

August 2022

Preliminary Engineering Initiated

Aug
2023

Spring 2023

Project website launch

May
2024

March/April 2024

Preliminary Engineering Public Information Center

Mar

April 2024

Obtain Environmental Clearances

Apr

November 2024

Preliminary Engineering Complete

Nov
2025

January 2025

Final Design Initiated

Jan
2026

May 2026

Final Design Public Information Center

May

Advanced Contracts (Fall 2026)

ACE Shoulder Repair MP 31.90 To 40.10 Exit 7 Sicklerville Road Ramp Widening

Sep
2027

Contract 1 (2027–2029)

Rt 42 / ACE Interchange To MP 40.0

Jan
2029

Contract 2 (TBD)

ACE Eastbound Roadway MP 40.0 To 31.6

Jan

Contract 3 (TBD)

ACE Westbound Roadway MP 40.0 To 31.6

Jan